A department manager is given a budget target that she regards as impossible to achieve, and she has had no involvement in setting it. Which behavioural outcome is most likely?
Reduced motivation and possible disregard of the budget is most likely. When managers see targets as unachievable and have no say in setting them, they lack commitment, so the budget stops working as a motivational and control tool.
- AIncreased motivation because the target is stretching
- BReduced motivation and possible disregard of the budgetCorrect
- CImproved goal congruence across the organisation
- DElimination of budgetary slack
Explanation
Targets seen as unattainable and imposed without participation typically demotivate managers, who may then ignore the budget. Slack is more likely to be built in under participation, and congruence is unlikely to improve.
Did you get it right without looking?
One question tells you little. A timed set on Budget preparation shows your real accuracy, how long you take and where you lose marks.
More Budget preparation questions
- Zeta Co expects to sell 8,000 units next month. Opening inventory of finished goods is 1,500 units and the company wants closing inventory o…
- Quill Co makes 6,000 units of a product, each needing 5 kg of material at $4 per kg. Opening material inventory is 3,000 kg. Closing invento…
- Kestrel Co makes three products with the following data per unit: Product A contribution $24, uses 4 labour hours; Product B contribution $2…
- A company budgets sales of 12,000 units for next period. Opening inventory of finished goods is 1,500 units and the closing inventory target…
- The master budget of Orwell Co consists of which of the following?
- A company uses a rolling budget of four quarters, updated each quarter. The original annual budget for quarters 1 to 4 had direct labour of …