A department's budget is $200,000 of controllable costs. Under a participative approach, the manager proposes a budget of $230,000 by building in extra allowances, and it is agreed. The most accurate description of this behaviour is:
This is budgetary slack. The manager deliberately builds extra cost allowance, here $30,000 above the expected $200,000, into the budget to make the target easier to meet. It is a known risk of participative budgeting and reduces goal congruence.
- ABudgetary slackCorrect
- BIncremental budgeting
- CZero-based budgeting
- DGoal congruence
Explanation
Deliberately overstating costs to make the target easier to achieve is budgetary slack. Here $30,000 is built in above the $200,000 expected need. Incremental and zero-based describe budget methods, not this behaviour, and goal congruence is the alignment of goals, which slack undermines.
Did you get it right without looking?
One question tells you little. A timed set on Behavioural aspects of budgeting shows your real accuracy, how long you take and where you lose marks.
More Behavioural aspects of budgeting questions
- A budget is set at a level the manager believes is impossible to achieve. Which is the most likely behavioural consequence?
- Under a participative budgeting system, a manager expects to sell 10,000 units but submits a sales budget of 8,000 units so that the target …
- A department manager's budgeted expenditure for the year is $200,000. Her bonus is paid only if actual spending does not exceed budget. Near…
- According to research on target-setting and motivation, which budget target is most likely to produce the best performance from a manager?
- A company finds that its managers spend all of their allocated budget each year, even when they could save money, because they fear next yea…
- A manager is told by senior management to meet a budget that has been set entirely without any input from her or her team. Which behavioural…