CMA Final · Strategic Cost Management · Product Life Cycle Costing
A firm finds that about 70% of a product's life cycle cost is committed during design, although only about 10% has been spent by then. What is the main management implication?
Cost reduction effort should focus on the design stage. Most life cycle cost is committed by design decisions even though little cash has yet been spent, so changes made early are cheapest and most effective, while later control can influence only the remaining small share.
- ACost reduction effort should concentrate on the design stage, where cost is determinedCorrect
- BCost control should be deferred until the production stage
- CDesign costs should be ignored as sunk
- DOnly the decline stage offers scope for reduction
Explanation
Costs are largely locked in at design even if cash is spent later, so influence over cost is greatest early. Techniques such as target costing and design for manufacture exploit this. Deferring control to production forfeits most savings.
Did you get it right without looking?
One question tells you little. A timed set on Product Life Cycle Costing shows your real accuracy, how long you take and where you lose marks.
More Product Life Cycle Costing questions
- A product's life cycle cost is the total of costs incurred from design through to withdrawal and support. Which of the following costs would…
- During which stage of the product life cycle do firms typically incur the highest promotional spend relative to sales while profits are nega…
- In which stage of the product life cycle are marketing costs typically highest relative to sales, because of advertising and distribution bu…
- A product has total life cycle costs of Rs 120 lakh over 4 years, of which Rs 30 lakh is incurred before launch. Design decisions made in th…
- Vihaan Electronics launches a gadget. Total life cycle revenue is Rs 3,00,00,000 from 50,000 units. Upstream costs are Rs 40,00,000, product…
- Which of the following best describes the typical committed-cost pattern in product life cycle costing for a manufactured product?