ACCA Applied Knowledge · Management Accounting · Cost accounting methods

A firm of accountants charges clients on the basis of chargeable hours. Staff cost $90,000 for 2,000 available hours, of which 75% are chargeable. Other overheads are $30,000. What cost per chargeable hour should be used to recover all costs?

The cost per chargeable hour is $80. Total costs of $120,000 are divided by 1,500 chargeable hours, being 75% of 2,000 available hours, so non-chargeable time is recovered through the chargeable hours.

  1. A$80Correct
  2. B$60
  3. C$45
  4. D$120

Explanation

Total cost = 90,000 + 30,000 = $120,000. Chargeable hours = 2,000 x 75% = 1,500. Cost per chargeable hour = 120,000 / 1,500 = $80. $60 uses all 2,000 hours, which wrongly ignores non-chargeable time; $45 excludes overheads and uses available hours incorrectly.

Did you get it right without looking?

One question tells you little. A timed set on Cost accounting methods shows your real accuracy, how long you take and where you lose marks.

More Cost accounting methods questions