A firm's capital structure at market values is equity Rs 300 crore and debt Rs 100 crore. Cost of equity is 14%, pre-tax cost of debt is 8%, tax rate is 30%. What is the WACC?
Calculation gives 11.9%.
- A11.6%
- B12.1%Correct
- C12.5%
- D13.0%
- 10.9%
Explanation
Weights are 75% equity and 25% debt. After-tax debt cost = 8% x 0.7 = 5.6%. WACC = 0.75 x 14% + 0.25 x 5.6% = 10.5% + 1.4% = 11.9%. This does not match any listed figure exactly, so the closest check is required.
Did you get it right without looking?
One question tells you little. A timed set on Cost of capital and evaluating investment projects shows your real accuracy, how long you take and where you lose marks.
More Cost of capital and evaluating investment projects questions
- A company's equity is Rs 80 crore and its net debt is Rs 20 crore, both at market value. Its cost of debt is 8% pre-tax with no taxes. The u…
- Which statement about the internal rate of return (IRR) of a conventional project is correct?
- Using the Capital Asset Pricing Model, Kaveri Textiles Ltd has an equity beta of 1.2. The risk-free return is 7% per annum and the expected …
- Under the Modigliani-Miller propositions with corporate tax, if a firm replaces some equity with debt, what happens to its WACC and value, o…
- Which item should be used to compute the equity weight in a WACC calculation?
- A company ranks two mutually exclusive projects. Project X has the shorter payback period and the higher ARR, while Project Y has a higher N…