Skip to content

FRM Part I · FRM Exam Part I · How Do Firms Manage Financial Risk?

A fund holds a stock portfolio worth USD 20 million with a beta of 1.2 relative to the index. Index futures trade at 4,000 with a multiplier of USD 250 per index point. The fund wants to reduce beta to 0.6 using futures. What position should it take?

The fund should short 12 contracts. Each contract is worth 4,000 × 250 = USD 1 million, and reducing beta by 0.6 on a USD 20 million portfolio requires 0.6 × 20 million / 1 million = 12. Shorting 24 would take beta to zero rather than 0.6.

  1. AShort 12 contractsCorrect
  2. BShort 24 contracts
  3. CShort 6 contracts
  4. DShort 30 contracts

Explanation

Contract value = 4,000 x 250 = USD 1,000,000. Number = (beta_current - beta_target) x P / contract value = (1.2 - 0.6) x 20,000,000 / 1,000,000 = 12 short. Short 24 would reduce beta to zero (1.2 x 20). Short 6 uses a 0.3 difference, and 30 is wrongly using 1.5.

Did you get it right without looking?

One question tells you little. A timed set on How Do Firms Manage Financial Risk? shows your real accuracy, how long you take and where you lose marks.

More How Do Firms Manage Financial Risk? questions