A job costing system differs from batch costing mainly because in job costing:

Job costing costs each job separately, normally produced to a particular customer's specification. Batch costing instead treats a group of identical units as a single cost unit. Continuous averaging applies to process costing, so the first option is correct.

  1. AEach job is usually executed to a customer's specific order and costed separatelyCorrect
  2. BEach job always consists of many identical units
  3. CCosts are averaged over a continuous production flow
  4. DCosts are never traced to cost units

Explanation

Job costing accumulates costs for a specific customer order, which is distinct. Batch costing groups identical units into one cost unit. Continuous flow averaging belongs to process costing.