A Kochi firm uses a three-month simple moving average to forecast demand. Actual demand for the last three months was 120, 150 and 180 units. Using exponential smoothing alternatively with α = 0.5, the previous forecast was 140 and actual was 180. What is the exponential smoothing forecast for the next month?

The exponential smoothing forecast is 160 units. With alpha 0.5, the new forecast is half the latest actual of 180 plus half the previous forecast of 140, giving 90 plus 70. The figure of 150 comes from the moving average, which is a different method.

  1. A150
  2. B160Correct
  3. C180
  4. D140

Explanation

Forecast = α×Actual + (1-α)×Previous forecast = 0.5×180 + 0.5×140 = 90 + 70 = 160. The moving average would be 150, which is the distractor from using the wrong method. Using 180 ignores smoothing.

Did you get it right without looking?

One question tells you little. A timed set on Introduction to Tools for Data Analytics shows your real accuracy, how long you take and where you lose marks.

More Introduction to Tools for Data Analytics questions