Skip to content

CMA Final · Strategic Cost Management · Introduction to Tools for Data Analytics

A Kolkata company uses a 3-month centred moving average to smooth monthly demand (units): Jan 100, Feb 120, Mar 110, Apr 130, May 140, Jun 150. Using a simple 3-month moving average, what is the forecast for July, and what is the smoothed value centred on April?

The July forecast is 140 units and the April-centred smoothed value is 126.67. The forecast averages the latest three months, April to June, giving 420/3. The centred April value averages March, April and May, giving 380/3.

  1. AJuly forecast 140; April smoothed 120
  2. BJuly forecast 140; April smoothed 126.67Correct
  3. CJuly forecast 150; April smoothed 126.67
  4. DJuly forecast 126.67; April smoothed 140

Explanation

July forecast = average of Apr, May, Jun = (130+140+150)/3 = 140. The value centred on April = (Mar+Apr+May)/3 = (110+130+140)/3 = 126.67. Using Feb-Mar-Apr gives 120, which is centred on March, not April.