Skip to content

FRM Part I · FRM Exam Part I · Interest Rates

A manager holds a $50 million bond portfolio with a modified duration of 6.0 and wants to reduce its duration to 2.0 using Treasury bond futures. Each futures contract is priced at $120,000 and has a duration of 8.0. Which position is closest to the required hedge?

Short about 208 contracts. The duration-based hedge is (2 - 6) x $50 million divided by (8 x $120,000), which is about -208.3. The negative sign means selling futures. Shorting 313 would remove all duration, which overshoots the target of 2.

  1. ALong 208 contracts
  2. BShort 104 contracts
  3. CShort 208 contractsCorrect
  4. DShort 313 contracts

Explanation

Contracts = (target duration - current duration) x P / (futures duration x futures price) = (2 - 6) x 50,000,000 / (8 x 120,000) = -200,000,000 / 960,000 = -208.3, so short about 208. Short 313 is the full hedge to zero duration (6 x 50m / 960,000 = 312.5). Short 104 uses the target duration instead of the change.

Did you get it right without looking?

One question tells you little. A timed set on Interest Rates shows your real accuracy, how long you take and where you lose marks.