FRM Part II · FRM Exam Part II · VaR and Risk Budgeting in Investment Management
A manager's signals have an IC of 0.05 and she makes 100 independent bets a year. Because of a long-only constraint, her transfer coefficient is 0.60. Using the extended fundamental law, IR = TC x IC x sqrt(breadth), what is her expected information ratio?
The expected information ratio is 0.30. Without constraints, IC of 0.05 times the square root of 100 gives 0.50. The transfer coefficient of 0.60 scales this down for the long-only constraint, so 0.60 times 0.50 equals 0.30.
- A0.50
- B0.30Correct
- C0.83
- D0.03
Explanation
Unconstrained IR = 0.05 x sqrt(100) = 0.50. Applying TC of 0.60 gives 0.50 x 0.60 = 0.30. The 0.50 option ignores the constraint, 0.83 divides by TC, and 0.03 uses breadth of 1 with TC wrongly.
Did you get it right without looking?
One question tells you little. A timed set on VaR and Risk Budgeting in Investment Management shows your real accuracy, how long you take and where you lose marks.
More VaR and Risk Budgeting in Investment Management questions
- A manager wants to double the information ratio of a strategy while holding IC and the transfer coefficient constant. According to the funda…
- A fund holds two managers with standalone active risk (tracking error) of 3% for Manager A and 4% for Manager B. Their active returns are un…
- A sponsor evaluates two managers using information ratios (IR). Manager A has alpha of 2.4% with tracking error of 4%. Manager B has alpha o…
- A portfolio manager has an information coefficient (IC) of 0.05, makes 100 independent, equally weighted bets per year, and assumes the basi…
- A fund manager compares two portfolios using the Sharpe ratio. Portfolio A has an expected return of 9%, volatility of 12%, and the risk-fre…
- A pension fund sets a total active risk budget of 4% tracking error and allocates it among three external managers. Which statement best des…