ACCA Strategic Professional · Strategic Business Leader · Cost and management accounting
A manufacturer using a standard costing system finds that the material price variance has been adverse for six months after a key supplier was replaced following a sustainability audit. Which interpretation is most appropriate for management accounting purposes?
The adverse variance stems from a deliberate sourcing decision, so it is partly a planning variance rather than poor buying. If the new supplier is permanent, the standard should be revised, and managers should be judged on controllable operational variances only.
- ATreat the variance as partly uncontrollable and planned, and revise the standard if the new supplier is permanentCorrect
- BPenalise the purchasing manager because adverse price variances always indicate poor buying
- CIgnore the variance because standards must never be changed
- DTreat it as a usage variance caused by production inefficiency
Explanation
The variance results from a deliberate decision, so it is not simply poor buying. If the change is permanent, the standard is out of date and should be revised, with the variance split into planning and operational elements.
Did you get it right without looking?
One question tells you little. A timed set on Cost and management accounting shows your real accuracy, how long you take and where you lose marks.
More Cost and management accounting questions
- Harbour Logistics Ltd has always set next year's budget by taking this year's actual costs and adding 4% for inflation. Managers say this le…
- Harlow Foods, a manufacturer with a single bottleneck machine, has been trying to maximise the utilisation of all workers and machines to re…
- Lakeshore Printing's management accountant notes that as output rises beyond normal capacity, the cost per extra unit initially falls due to…
- Halden Pharma operates in a market where regulatory approvals and competitor launches change quickly, making a 12-month fixed budget out of …
- Brightwell Hospital's budget for its maintenance department has been cut by the board. The department head argues that the budget should be …
- Lindqvist Components budgeted to produce and sell 10,000 units at a variable cost of $12 per unit and fixed costs of $50,000. Actual output …