FRM Part II · FRM Exam Part II · VaR and Risk Budgeting in Investment Management
A plan sponsor's total portfolio has an annual VaR of 10 million. Manager X has a standalone VaR of 6 million and a component (marginal-based) VaR contribution of 4 million. If the sponsor removes Manager X's positions entirely, which is the best first-order estimate of the total VaR change using the component VaR?
The best estimate is a reduction of about 4 million. Component VaR is the manager's contribution to portfolio VaR after diversification, so it approximates the effect of removing the position. Standalone VaR of 6 million ignores diversification benefits and would overstate the reduction.
- AA reduction of about 6 million, the standalone VaR
- BA reduction of about 4 million, the component VaRCorrect
- CA reduction of about 10 million
- DNo change, since component VaR is only an accounting allocation
Explanation
Component VaR measures a position's contribution to total portfolio VaR so contributions sum to total VaR; it approximates the change from removing the position. Standalone VaR ignores diversification and overstates the reduction.
Did you get it right without looking?
One question tells you little. A timed set on VaR and Risk Budgeting in Investment Management shows your real accuracy, how long you take and where you lose marks.
More VaR and Risk Budgeting in Investment Management questions
- A risk committee sets a mandate for an index-tracking fund. Which risk limit is most appropriate for monitoring whether the manager is stayi…
- A manager wants to double the information ratio of a strategy while holding IC and the transfer coefficient constant. According to the funda…
- A portfolio has two assets with weights 60% and 40%, volatilities 20% and 10%, and correlation 0.5. Portfolio value is USD 100 million. Usin…
- A fund holds two managers with standalone active risk (tracking error) of 3% for Manager A and 4% for Manager B. Their active returns are un…
- A sponsor evaluates two managers using information ratios (IR). Manager A has alpha of 2.4% with tracking error of 4%. Manager B has alpha o…
- A portfolio manager has an information coefficient (IC) of 0.05, makes 100 independent, equally weighted bets per year, and assumes the basi…