A PMS portfolio has a return of 14%, the risk-free rate is 6% and the portfolio's standard deviation is 16%. What is its Sharpe ratio?

The Sharpe ratio is 0.50. It is the excess return over the risk-free rate, 14% minus 6% which is 8%, divided by the standard deviation of 16%. This measures return earned per unit of total risk.

  1. A0.50Correct
  2. B0.875
  3. C0.38
  4. D2.33

Explanation

Sharpe ratio = (Rp − Rf)/standard deviation = (14 − 6)/16 = 8/16 = 0.50. Using 14/16 = 0.875 forgets to subtract the risk-free rate. Dividing 6 by 16 gives 0.375, which uses the risk-free rate alone instead of the excess return.