A PMS portfolio manager's portfolio value rose from Rs 50,00,000 at the start of the year to Rs 56,00,000 at the end of the year, with no cash inflows or outflows during the year. What is the simple absolute return for the year?
The absolute return is 12%. The gain of Rs 6,00,000 is divided by the opening value of Rs 50,00,000, because return is always measured on the starting capital when there are no interim cash flows.
- A10%
- B12%Correct
- C14%
- D11.2%
Explanation
Absolute return = (56,00,000 - 50,00,000) / 50,00,000 = 6,00,000 / 50,00,000 = 12%. Choosing 10% comes from dividing the gain by the ending value incorrectly in a rounded way. Using the end value as the base gives 6/56 = 10.7%, which is also wrong. The start value is the correct base.
Did you get it right without looking?
One question tells you little. A timed set on Performance Measurement and Evaluation of Portfolio Managers shows your real accuracy, how long you take and where you lose marks.
More Performance Measurement and Evaluation of Portfolio Managers questions
- A PMS portfolio is worth Rs 50,00,000 at the start of the year and Rs 58,00,000 at the end, with no inflows or withdrawals. Its benchmark re…
- Which statement best describes the Treynor ratio used in evaluating portfolio managers?
- Which statement about the Sharpe ratio, used to evaluate a portfolio manager, is correct?
- A portfolio is worth Rs 10,00,000 at the start of the year. It grows to Rs 12,00,000 by mid-year, when the client adds Rs 4,00,000, making R…
- Which of the following measures uses beta rather than standard deviation as its measure of risk?
- A portfolio manager's PMS strategy earned a return of 14% in a year, while its chosen benchmark returned 11% over the same period. What is t…