A portfolio has a DV01 of $50,000 to a 2-year loading and $30,000 to a 10-year loading, both expressed as dollar loss per 1bp rise. Factor 1 (level) loads +1 and +1 on the 2-year and 10-year rates. Factor 2 (slope) loads -1 on the 2-year and +1 on the 10-year. What is the portfolio's loss per one-unit shock to each factor, (level, slope)?
The level exposure is a loss of $80,000 per unit and the slope exposure has magnitude $20,000. Level adds the two DV01s, 50,000 plus 30,000. Slope loads -1 on the 2-year and +1 on the 10-year, giving -50,000 plus 30,000, a net gain of $20,000 for steepening.
- ALevel: $80,000; slope: $20,000Correct
- BLevel: $80,000; slope: $80,000
- CLevel: $20,000; slope: $80,000
- DLevel: $20,000; slope: $20,000
Explanation
Loss for factor k = sum of DV01 times loading. Level: 50,000(1)+30,000(1) = 80,000. Slope: 50,000(-1)+30,000(1) = -20,000, meaning a gain of $20,000 for a steepening shock; the magnitude is 20,000. Option with 80,000 for slope ignores the sign of the loading, and the reversed options swap the factors.
Did you get it right without looking?
One question tells you little. A timed set on Modeling Non-Parallel Term Structure Shifts and Hedging shows your real accuracy, how long you take and where you lose marks.
More Modeling Non-Parallel Term Structure Shifts and Hedging questions
- A portfolio has key rate 01s (gain per 1 bp fall in the rate) of $200 at 2 years, $500 at 5 years and $800 at 10 years. Over a day the 2-yea…
- A portfolio's daily P&L has a standard deviation of $200,000. A hedge instrument's daily P&L has a standard deviation of $150,000, and the c…
- Key rates are set at 2, 5 and 10 years. A key rate shift is applied in which the 5-year rate rises by 10 bp, the 2-year and 10-year rates ar…
- A fund holds bonds with a DV01 of $12,000 per basis point, concentrated around the 7-year point. A 7-year interest rate swap has a DV01 of $…
- A PCA of yield curve changes yields eigenvalues (variances of the components) of 12.0, 4.0, 1.5 and 0.5 for the first four principal compone…
- A $20 million portfolio has key rate durations of 0.5 at the 2-year, 2.0 at the 5-year and 3.5 at the 10-year points. The 2-year key rate ri…