NISM Certifications · NISM-Series-XXI-A: Portfolio Management Services (PMS) Distributors · Portfolio Management Process
A portfolio has an average return of 14% a year, the risk-free rate is 6%, and the standard deviation of the portfolio is 16%. What is its Sharpe ratio?
The Sharpe ratio is 0.50. It is calculated by taking the excess return over the risk-free rate, which is 14% minus 6%, or 8%, and dividing by the portfolio's standard deviation of 16%. It shows the return earned per unit of total risk.
- A0.50Correct
- B0.875
- C0.38
- D2.00
Explanation
Sharpe ratio = (portfolio return - risk-free rate) / standard deviation = (14 - 6) / 16 = 0.50. Dividing 14 by 16 without deducting the risk-free rate gives 0.875, which is wrong because it ignores the excess return. Dividing 6 by 16 gives 0.38, which uses the wrong numerator.
Did you get it right without looking?
One question tells you little. A timed set on Portfolio Management Process shows your real accuracy, how long you take and where you lose marks.
More Portfolio Management Process questions
- Under SEBI Portfolio Managers Regulations, which statement about a discretionary PMS is correct?
- A portfolio is valued at Rs 10,00,000 at the start of a year. The portfolio manager's strategic asset allocation is 60% equity and 40% debt.…
- In the portfolio management process, which step is carried out first, before the portfolio manager selects securities for a client?
- A portfolio is worth Rs 10,00,000 at the start of the year. It consists of Rs 6,00,000 in equity that returns 15% and Rs 4,00,000 in debt th…
- A PMS portfolio started the year at Rs 50,00,000 and ended at Rs 56,00,000 with no inflows or outflows. Its benchmark returned 9% over the s…
- Which document records a client's return objective, risk tolerance, time horizon, liquidity needs and constraints to guide the portfolio man…