FRM Part II · FRM Exam Part II · Market-Driven Scenarios: An Approach for Plausible Scenario Construction
A portfolio has exposures to two factors, A and B. The scenario sets A's shock at -5.0%. A has volatility 2.5% and B has volatility 4.0%. The correlation is 0.40. The portfolio gains 8 million for each +1% move in A and loses 3 million for each +1% move in B. Using the conditional expected shock for B, what is the expected scenario P&L, in millions?
The expected scenario P&L is -30.4 million. B's conditional shock is 0.40 × (4.0/2.5) × -5% = -3.2%. A contributes 8 × -5 = -40 million, and B contributes -3 × -3.2 = +9.6 million because the portfolio is short B. Summing gives -30.4 million.
- A-40.0 million
- B-26.4 million
- C-13.6 millionCorrect
- D-30.4 million
Explanation
B's conditional shock = 0.40 × (4.0/2.5) × (-5%) = -3.2%. P&L from A = 8 × (-5) = -40. P&L from B = -3 × (-3.2) = +9.6. Total = -40 + 9.6 = -30.4 million. Check: the -26.4 option comes from using -2.4%... no; correct is -30.4. Option -30.4 million is therefore correct and the answer index must reflect this.
Did you get it right without looking?
One question tells you little. A timed set on Market-Driven Scenarios: An Approach for Plausible Scenario Construction shows your real accuracy, how long you take and where you lose marks.
More Market-Driven Scenarios: An Approach for Plausible Scenario Construction questions
- A risk team builds a stress scenario in which equity prices fall sharply. In a market-driven approach, how should the team set the moves in …
- After running a market-driven scenario, a risk manager finds that most of the portfolio loss comes from a single position with a concentrate…
- A risk team constructs a stress scenario by shocking the equity index by -3 standard deviations and then, to measure plausibility, computes …
- A risk team builds a market-driven scenario by choosing one risk factor to shock severely and then setting the other factors at their expect…
- An analyst builds a market-driven scenario assuming returns on a portfolio's risk factors are jointly normal with zero mean. Factor X (equit…
- A risk team builds a market-driven scenario by choosing one risk factor as the stress driver and then deriving the shocks to all other facto…