FRM Part II · FRM Exam Part II · Market-Driven Scenarios: An Approach for Plausible Scenario Construction
A portfolio holds an $80 million equity position with delta 1 to the equity index. It also has a credit spread sensitivity (CS01) of a $50,000 loss per 1 bp widening. In the scenario, the equity index falls 15%. The index has a standard deviation of 10%, spreads have a standard deviation of 40 bp, and their correlation is -0.5. Using conditional expected spread moves, what is the scenario loss?
The scenario loss is $13.5 million. The equity fall costs $12.0 million, and the conditional spread widening of 30 bp costs a further $1.5 million at $50,000 per bp. Both legs lose, so they add.
- A$13.5 millionCorrect
- B$12.0 million
- C$10.5 million
- D$15.0 million
Explanation
The spread move is -0.5 x (40/10) x (-15) = +30 bp. The equity loss is 80 x 15% = $12.0m and the credit loss is 30 x $50,000 = $1.5m, so the total is $13.5m. Ignoring the spread leg gives $12.0m. Treating the spread leg as a gain gives $10.5m.
Did you get it right without looking?
One question tells you little. A timed set on Market-Driven Scenarios: An Approach for Plausible Scenario Construction shows your real accuracy, how long you take and where you lose marks.
More Market-Driven Scenarios: An Approach for Plausible Scenario Construction questions
- A portfolio has exposures to two risk factors. A scenario shocks Factor A by -10%, and the estimated conditional relationship implies Factor…
- A risk team constructs a scenario by shocking the 10-year Treasury yield and using a historical covariance matrix to set the other factor mo…
- A risk manager at an asset manager builds a stress scenario by first choosing a small set of market variables, such as equity index and cred…
- A portfolio manager uses a market-driven approach in which a stress on a chosen core risk factor is propagated to other factors using their …
- A stress team is constructing a scenario for a portfolio exposed to factors A, B and C. They are deciding between anchoring on factor A or f…
- A risk committee notes that its scenario, built from conditional expected shocks using historical correlations, understates losses in a cris…