A portfolio manager earned a return of 14% in a year. The risk-free rate was 6%, the portfolio's standard deviation was 16% and its beta was 1.25. What is the Sharpe ratio of the portfolio?
The Sharpe ratio is 0.50. It is the excess return over the risk-free rate, 14% minus 6% equals 8%, divided by the portfolio's standard deviation of 16%. Beta is not used in the Sharpe ratio; it belongs in the Treynor ratio.
- A0.50Correct
- B0.64
- C0.875
- D0.40
Explanation
Sharpe ratio = (Rp - Rf) / standard deviation = (14 - 6) / 16 = 0.50. The value 0.64 is the Treynor ratio (8/1.25) in percentage terms, which uses beta instead of standard deviation. Using 14/16 gives 0.875, ignoring the risk-free rate.
Did you get it right without looking?
One question tells you little. A timed set on Portfolio Construction Process shows your real accuracy, how long you take and where you lose marks.
More Portfolio Construction Process questions
- Ms. Anjali Rao, 28, is a salaried professional with a high risk appetite, a 25-year horizon for retirement, and stable income. Which asset a…
- Meera Iyer invests Rs 10,00,000 for 3 years in a portfolio. Returns are +20% in year 1, -10% in year 2 and +25% in year 3. What is the appro…
- A portfolio is 60% in equity with an expected return of 12% and 40% in debt with an expected return of 7%. What is the expected return of th…
- Meera, aged 35, wants Rs 50,00,000 after 10 years for her child's education. She will invest a lump sum today in a portfolio expected to ear…
- Which asset allocation approach involves setting long-term target weights based on the client's risk profile and returns expectations, and t…
- Mr. Desai, 58, plans to retire in two years and will need a large part of his corpus for near-term expenses. He has low risk tolerance. Whic…