A portfolio of bonds has a market value of $1,200,000 and a modified duration of 6.5. What is its approximate DV01?
The DV01 is $780. DV01 is the dollar value change for a one basis point yield move, computed as modified duration times market value times 0.0001. Here that is 6.5 × 1,200,000 × 0.0001 = $780.
- A$780Correct
- B$7,800
- C$78
- D$1,560
Explanation
DV01 = modified duration × market value × 0.0001 = 6.5 × 1,200,000 × 0.0001 = $780 per basis point. The $7,800 option scales by 0.001 instead of 0.0001, which is a factor-of-ten error.
Did you get it right without looking?
One question tells you little. A timed set on Modeling Non-Parallel Term Structure Shifts and Hedging shows your real accuracy, how long you take and where you lose marks.
More Modeling Non-Parallel Term Structure Shifts and Hedging questions
- A portfolio has key-rate DV01 exposures of +$40,000 at the 2-year, -$10,000 at the 5-year and -$20,000 at the 10-year (per 1 bp fall in the …
- A bond portfolio has key-rate 01s (the gain for a 1 bp fall in each key rate) of $3,000 at the 2-year point, $5,000 at the 5-year point and …
- A portfolio has exposures (change in value per 1 bp rise in the rate) to the 2-year, 5-year and 10-year rates of -$40,000, -$10,000 and +$30…
- A risk manager regresses daily P&L changes of a bond portfolio on daily P&L changes of a futures hedge and obtains an R-squared of 0.84. The…
- A portfolio has key-rate exposures of $20,000 per bp at the 2-year point and $40,000 per bp at the 10-year point (it loses that amount per 1…
- A portfolio manager holds a liability with a DV01 of USD 42,000 and hedges with two bonds: Bond A has DV01 of USD 600 per USD 1 million face…