A project costs Rs 100,000 now and returns Rs 55,000 at time 1 and Rs 60,500 at time 2 (its internal rate of return is 10% per annum). The firm can borrow at 8% effective per annum. What is the net present value of the project at 8% per annum?
The NPV is Rs 2,794.93. At 8% the loan clears with a surplus of Rs 3,260 at time 2, and discounting this by 1.08 squared gives Rs 2,794.93. Because the internal rate of return of 10% exceeds 8%, the NPV is positive.
- ARs 0.00
- BRs 2,794.93Correct
- CRs 3,260.00
- DRs 6,944.44
- -Rs 2,794.93
Explanation
Loan balance: -100,000 x 1.08 + 55,000 = -53,000. At time 2: -53,000 x 1.08 + 60,500 = 3,260. Discount to time 0: 3,260 / 1.1664 = 2,794.93. Rs 3,260 is the time-2 value, not the present value. Rs 6,944.44 discounts the second flow for only one year.
Did you get it right without looking?
One question tells you little. A timed set on Project appraisal shows your real accuracy, how long you take and where you lose marks.
More Project appraisal questions
- An investment requires Rs 10,000 now and pays Rs 5,500 at the end of year 1 and Rs 6,050 at the end of year 2. What is the internal rate of …
- An investment of ₹1,000 at time 0 produces cashflows of ₹600 at the end of year 1 and ₹600 at the end of year 2. What is the IRR, to two dec…
- A project requires an outlay of Rs 50,000 now and pays Rs 20,000 at the end of each half-year for 18 months (three payments). The cost of ca…
- A project pays Rs 33,000 at the end of year 1 and Rs 48,400 at the end of year 2. At an effective annual rate of 10%, what initial outlay wo…
- A project costs ₹10,00,000 now and returns ₹6,00,000 at the end of year 1 and ₹5,50,000 at the end of year 2. What is its internal rate of r…
- A project has net cashflows of −₹100 at time 0, +₹230 at time 1 and −₹132 at time 2. Which statement about its IRR is correct?