A regional bank plans to outsource its card-processing operations to a vendor. Which activity should the bank complete first in the third-party risk management lifecycle, before negotiating the contract?

Planning and risk assessment comes first. The bank must decide why it is outsourcing, how critical the activity is and what risks arise before selecting a vendor, performing due diligence or negotiating a contract. Monitoring and termination happen later in the lifecycle.

  1. APlanning and risk assessment of the outsourcing arrangement, including its criticalityCorrect
  2. BOngoing performance monitoring of the vendor's service levels
  3. CExecution of the exit strategy and transition of services
  4. DAnnual review of the vendor's incident reports

Explanation

The lifecycle begins with planning and risk assessment, where the bank determines the strategic rationale, criticality and risks of the activity. Due diligence, contracting, monitoring and termination follow. Monitoring and exit activities occur only after a vendor is engaged.