FRM Part II · FRM Exam Part II · Validating Bank Holding Companies' Value-at-Risk Models for Market Risk
A risk manager at a bank holding company observes 8 exceptions in 250 days for a 99% one-day VaR model. Using the Basel traffic-light zones (green 0-4, yellow 5-9, red 10 or more), what is the most appropriate conclusion?
Eight exceptions out of 250 sits in the yellow zone. Results there are ambiguous, so the model is not automatically rejected, but supervisors can raise the capital multiplier, depending on the cause. Too many exceptions suggests risk may be underestimated rather than overestimated.
- AGreen zone; the model is accepted with no change in the capital multiplier
- BYellow zone; the model may be inaccurate and the supervisor may increase the capital multiplierCorrect
- CRed zone; the model is automatically rejected
- DYellow zone; the multiplier is cut because the model is conservative
Explanation
Eight exceptions falls in the yellow zone (5-9). Here the model is not automatically rejected, but supervisors may add to the multiplier, with discretion depending on the cause. The red zone begins at 10, and more exceptions than expected implies underestimated risk, not conservatism.
Did you get it right without looking?
One question tells you little. A timed set on Validating Bank Holding Companies' Value-at-Risk Models for Market Risk shows your real accuracy, how long you take and where you lose marks.
More Validating Bank Holding Companies' Value-at-Risk Models for Market Risk questions
- A validation team at a bank holding company finds that its VaR model's 99% one-day VaR is consistently well below that of a benchmark model,…
- A risk analyst applies Kupiec's proportion-of-failures (unconditional coverage) test to a 99% one-day VaR model. Which statement correctly d…
- A bank holding company's model validation group is asked to describe the core purpose of validating the bank's trading VaR model. Which of t…
- A supervisory review of several bank holding companies found that reported trading VaR was often much lower than the profit and loss variabi…
- A bank backtests a 99% VaR model over 250 days with 6 exceptions. Using the approximation that the number of exceptions is normal with mean …
- A risk manager backtests a 99% one-day VaR model over 500 days and observes 11 exceptions. Using the unconditional coverage (Kupiec proof-of…