A risk manager has a regression with two highly correlated regressors whose coefficients are individually insignificant. Which statement about the consequences and treatment of this perfect-to-high (but not perfect) multicollinearity is correct?
Under imperfect multicollinearity, OLS estimates stay unbiased but their standard errors are inflated, so individual t-tests lose power. A joint F-test on the correlated variables can still show they are significant together, and the model can still forecast well if the correlation pattern persists.
- AOLS coefficient estimates become biased, so the model must be discarded
- BForecasts from the model are necessarily invalid even for observations with the same correlation structure
- CCoefficient estimates remain unbiased but have inflated standard errors, and a joint F-test on the two coefficients can still show they matterCorrect
- DThe R-squared of the regression is mechanically forced to be close to zero
Explanation
With imperfect multicollinearity, OLS remains unbiased and consistent, but standard errors rise, making individual t-tests unreliable. A joint F-test on the correlated variables can still detect their combined significance. Forecasts can remain reasonable if the correlation structure persists. R-squared is not forced down.
Did you get it right without looking?
One question tells you little. A timed set on Regression with Multiple Explanatory Variables shows your real accuracy, how long you take and where you lose marks.
More Regression with Multiple Explanatory Variables questions
- In a two-regressor model, the standard error of the slope on X1 is 0.30 when X1 and X2 are correlated with an auxiliary R-squared of 0.75. H…
- A researcher models bond spread changes using quarterly data and wants to capture seasonal effects with an intercept for each of the four qu…
- A researcher estimates an unrestricted regression with 5 explanatory variables and an intercept on 124 observations, getting R-squared of 0.…
- In a multiple regression, the standard error of a slope coefficient would be 0.040 if its regressor were uncorrelated with the other regress…
- A risk manager models quarterly loss rates using an intercept and three seasonal dummy variables (Q2, Q3, Q4) with Q1 as the base period, an…
- A model of credit spreads is first estimated with 3 explanatory variables on 60 observations, giving a residual sum of squares (RSS) of 48. …