FRM Part II · FRM Exam Part II · Supervisory Guidance on Model Risk Management
A risk manager is asked what a bank's model risk policy should say when a model with known limitations must be used before validation is complete. Which provision best fits supervisory guidance?
The policy should allow use only as a documented, approved exception with compensating controls, such as conservative adjustments or limits, and a set deadline for completing validation. Developer sign-off or a lack of losses is not sufficient, and an absolute ban is not what guidance requires.
- AUse should be permitted only as an approved exception, with documented rationale, compensating controls such as conservative overlays and limits, and a deadline for completing validationCorrect
- BUse should be permitted freely provided the developer signs off on accuracy
- CUse should be prohibited in all circumstances, with no exceptions
- DUse should be allowed indefinitely if no losses have occurred
Explanation
Guidance recognizes that exceptions may be needed but requires them to be controlled: documented, approved, accompanied by compensating controls and time-bound. Developer sign-off is not independent, a blanket ban ignores practical needs, and absence of losses does not demonstrate model soundness.
Did you get it right without looking?
One question tells you little. A timed set on Supervisory Guidance on Model Risk Management shows your real accuracy, how long you take and where you lose marks.
More Supervisory Guidance on Model Risk Management questions
- A bank's VaR model shows 9 exceptions in 250 days at 99% confidence, while a validator notes the model passed an annual back-test last year.…
- According to SR 11-7, which statement about the relationship between model risk and model uncertainty is most accurate?
- A bank maintains a model inventory. An internal audit finds that several spreadsheet tools used to price illiquid positions are not listed b…
- A bank uses a model built for retail mortgage loss forecasting to estimate losses on a newly acquired commercial real estate book, reasoning…
- A bank wishes to use a vendor-supplied credit scoring model whose code is proprietary and cannot be shared. The model owner proposes skippin…
- A risk manager is asked to describe an aggregate view of model risk across the firm to the board. Which approach is most consistent with sup…