FRM Part II · FRM Exam Part II · Liquidity Stress Testing
A risk manager is calibrating the horizon for a liquidity stress scenario for a bank reliant on wholesale funding. Which approach is most appropriate?
Multiple horizons, from overnight through weeks to several months, are most appropriate. Liquidity stress evolves over time with different outflow drivers at each stage, so using several horizons shows when the buffer is exhausted. A single overnight or one-year horizon would miss critical timing of shortfalls.
- AUse a single overnight horizon because liquidity problems resolve within one day
- BUse multiple horizons, such as overnight, one week, one month and three months or longer, to capture evolving outflow dynamicsCorrect
- CUse only a one-year horizon to align with the capital planning cycle
- DUse a horizon equal to the average maturity of the bank's assets
Explanation
Liquidity stress unfolds over different time frames: immediate intraday and overnight needs, then short-term funding runoff, then longer structural pressure. Multiple horizons reveal when the survival period ends. A single horizon, even a long one, hides the timing of shortfalls.
Did you get it right without looking?
One question tells you little. A timed set on Liquidity Stress Testing shows your real accuracy, how long you take and where you lose marks.
More Liquidity Stress Testing questions
- A bank's treasury head explains that the Basel III Liquidity Coverage Ratio (LCR) is designed to ensure survival over a specific stress hori…
- Which asset is generally the best candidate for inclusion in a bank's core liquidity buffer used for stress testing?
- A risk manager distinguishes between funding liquidity risk and market liquidity risk. Which situation is the clearest example of funding li…
- A bank's validation team reviews its liquidity stress testing governance. Which finding would be the most serious weakness?
- A risk manager reviews a liquidity stress test in which the buffer is composed mostly of one issuer's bonds and the survival horizon is repo…
- A bank's treasury team designs its liquidity stress testing program. The Chief Risk Officer asks who should hold ultimate accountability for…