FRM Part II · FRM Exam Part II · Counterparty Risk and Beyond
A risk manager simulates the future value of a portfolio with a counterparty. At a given future date, the simulated portfolio values (USD million) across ten equally likely scenarios are: -6, -2, 0, 1, 3, 4, 6, 8, 10, 14. What is the expected exposure (EE) at that date?
Expected exposure is USD 4.6 million. Exposure in each scenario is the portfolio value floored at zero. The positive values sum to 46 million, and dividing by the ten equally likely scenarios gives 4.6 million.
- AUSD 3.8 million
- BUSD 4.6 millionCorrect
- CUSD 4.8 million
- DUSD 5.2 million
Explanation
Exposure in each scenario is max(value,0). Positive values: 1+3+4+6+8+10+14 = 46; the other scenarios contribute 0. EE = 46/10 = 4.6 million. The 3.8 million figure averages raw values including negatives (38/10), which wrongly lets negative values offset positive ones.
Did you get it right without looking?
One question tells you little. A timed set on Counterparty Risk and Beyond shows your real accuracy, how long you take and where you lose marks.
More Counterparty Risk and Beyond questions
- A risk manager reviews a variation-margin agreement with daily margin calls. The counterparty defaults, and the bank's close-out of position…
- A bank's desk computes a unilateral CVA of 2.0 million and a DVA of 0.5 million on a netting set. Funding costs on uncollateralised exposure…
- A bank has two trades with the same counterparty under an enforceable netting agreement: Trade A has a mark-to-market of +USD 12 million and…
- A dealer bank prices a new uncollateralised interest rate swap with a corporate client. In addition to the risk-free value, the trader adds …
- A bank has an uncollateralised derivative with a counterparty. Using a simple discrete CVA formula with no wrong-way risk, the loss given de…
- A risk manager compares counterparty credit risk with the credit risk of a standard loan. Which statement correctly describes a key differen…