CMA Final · Strategic Financial Management · Securitization

A securitized pool has outstanding principal of ₹80 crore at the start of a month. During the month the obligors prepay ₹2 crore beyond the scheduled principal repayment of ₹3 crore. Ignoring interest, what is the pool factor at the end of the month, taking pool factor as outstanding principal divided by the original principal of ₹100 crore?

The pool factor is 0.75. Scheduled repayment of ₹3 crore plus prepayment of ₹2 crore reduces the outstanding balance from ₹80 crore to ₹75 crore. Dividing by the original principal of ₹100 crore gives 0.75.

  1. A0.77Correct
  2. B0.75
  3. C0.80
  4. D0.78

Explanation

Total principal reduction = 3 + 2 = ₹5 crore. Closing balance = 80 - 5 = ₹75 crore. Pool factor = 75/100 = 0.75. Wait: recompute shows 0.75, so the correct choice is 0.75.

Did you get it right without looking?

One question tells you little. A timed set on Securitization shows your real accuracy, how long you take and where you lose marks.

More Securitization questions