CS Executive · Economic, Commercial and Intellectual Property Laws · Real Estate Regulation and Development Law
A State Government has notified that it will set up a Real Estate Regulatory Authority but the Authority is not yet established. Under the RERA Act, 2016, what must the appropriate Government do in the meantime?
Until the Real Estate Regulatory Authority is established, the appropriate Government must by order designate any Regulatory Authority or any officer, preferably the Secretary of the Housing department, to act as the Regulatory Authority. Projects and complaints are not suspended or left unregulated in the interim.
- ASuspend the registration of all real estate projects until the Authority is established
- BDesignate by order any Regulatory Authority or any officer, preferably the Secretary of the Housing department, as the Regulatory AuthorityCorrect
- CTransfer all complaints to the Central Advisory Council
- DAllow promoters to sell units without registration until establishment
Explanation
Section 20 provides that until a Regulatory Authority is established, the appropriate Government shall by order designate any Regulatory Authority or any officer, preferably the Secretary of the department dealing with Housing. Suspending registration or permitting unregistered sales has no basis in the provision. The Central Advisory Council is advisory and does not hear complaints.
Did you get it right without looking?
One question tells you little. A timed set on Real Estate Regulation and Development Law shows your real accuracy, how long you take and where you lose marks.
More Real Estate Regulation and Development Law questions
- A State Government designated its Housing Secretary as interim Regulatory Authority, and a buyer's complaint is being heard by him. Later, t…
- Sharma Developers fails to give possession of Kavita's flat as per the agreement for sale. Under section 19 of RERA, 2016, which right is av…
- Sunrise Builders of Pune plans a residential project of 20 apartments on 2,000 sq m of land and wants to start inviting bookings through new…
- Sunrise Developers' project registration was revoked by the Authority for violations. Meera, a prospective buyer, wants to check whether the…
- Greenview Homes Pvt Ltd, a promoter in Pune, is aggrieved by an order of the Maharashtra Real Estate Regulatory Authority directing it to re…
- Kaveri Realty Pvt Ltd, a promoter in Pune, is planning to launch a housing project. A colleague asks which body is empowered under the RERA …