Skip to content

CS Professional · Drafting, Pleadings and Appearances · Drafting of Commercial Contracts

A supply agreement drafted for Kaveri Foods says: 'Kaveri shall buy 500 tonnes of rice from Anand Traders at a fixed price if the Government of Tamil Nadu does not lift its stock limit before 31 March.' Which drafting consequence follows from this contingent clause?

The purchase obligation is enforceable if 31 March passes without the stock limit being lifted, or earlier if it becomes certain that it will not be lifted. Until then the contingent clause is not enforceable, and it is not void merely because a third party is involved.

  1. AKaveri must buy at once, since contingent clauses bind from signing
  2. BThe clause is void unless the Government lifts the limit
  3. CThe agreement is void because it depends on a third party
  4. DThe purchase obligation becomes enforceable when the limit is lifted... not applicable; it is enforceable if 31 March passes without the limit being lifted, or earlier if lifting becomes impossibleCorrect

Explanation

Section 35 says a contract contingent on an event not happening within a fixed time can be enforced when the time expires without the event, or earlier if it becomes certain the event will not happen. So the purchase obligation arises only then. Immediate enforcement ignores the contingency, and voidness would apply only to contracts needing the event to happen.

Did you get it right without looking?

One question tells you little. A timed set on Drafting of Commercial Contracts shows your real accuracy, how long you take and where you lose marks.

More Drafting of Commercial Contracts questions