CS Professional · Arbitration, Mediation and Conciliation · Preparation and Execution of Arbitral Award
A tribunal awards Rs 40,00,000 to Veena Constructions against Omkar Infra. The award is silent on post-award interest and the parties have not agreed otherwise. On the date of award the current rate of interest under the Interest Act, 1978 is 9% per annum. What interest applies from the date of award to the date of payment?
Interest runs at 11% per annum. Under Section 31(7)(b), unless the award directs otherwise, the awarded sum carries interest at two per cent above the current rate prevalent on the date of award, so 9% plus 2% gives 11% from award to payment.
- ANo interest, because the award is silent
- B9% per annum
- C11% per annumCorrect
- D2% per annum
Explanation
Section 31(7)(b) provides that, unless the award otherwise directs, a sum awarded carries interest at two per cent higher than the current rate prevalent on the date of award, from award to payment. So 9% + 2% = 11%. Choosing 9% misses the 2% uplift; 2% alone uses the wrong base.
Did you get it right without looking?
One question tells you little. A timed set on Preparation and Execution of Arbitral Award shows your real accuracy, how long you take and where you lose marks.
More Preparation and Execution of Arbitral Award questions
- A three-member tribunal decided a dispute between Kavya Textiles and Ranjit Exports. After the award was drafted, one arbitrator refused to …
- Before any dispute arose, Verma Steels Ltd and Nair Traders signed an arbitration agreement stating that Nair Traders would pay the whole co…
- A three-member tribunal hears a construction dispute between Bharat Infra Ltd and Sundaram Steels Pvt Ltd in Chennai. At the time of signing…
- Parties to a dispute in Chennai agreed that the seat of arbitration would be Hyderabad, as determined under Section 20. The tribunal signed …
- A tribunal refuses to deliver its signed award to Desai Foods Ltd until Desai pays Rs 8,00,000 in fees demanded by the tribunal. No written …
- Under a supply contract, Bhatia Agro Ltd obtains an award against Orient Mills for Rs 50 lakh. The contract is silent on interest, and the a…