FRM Part II · FRM Exam Part II · Case Study: Model Risk and Model Validation
A validator backtests a one-day 99% VaR model over 250 trading days and observes 7 exceptions. Which conclusion is most appropriate?
Expected exceptions at 99% over 250 days are 2.5. Seven exceptions is materially higher, indicating the model may understate risk, so the validator should investigate causes such as stale data or wrong assumptions. It lands in the Basel yellow zone, not a clean pass.
- AThe model is acceptable, because 7 is below the 10 exceptions that would trigger a penalty
- BThe result is above the expected 2.5 exceptions, so the model may underestimate risk and warrants investigation of causesCorrect
- CThe model is overly conservative, because exceptions are fewer than 10
- DThe result is exactly in line with expectation for a 99% confidence level
Explanation
Expected exceptions are 250 x 1% = 2.5. Seven is well above that, suggesting possible underestimation of risk (under the Basel traffic-light approach it falls in the yellow zone). Option A misreads the red zone threshold as acceptability; seven is not in line with expectation.
Did you get it right without looking?
One question tells you little. A timed set on Case Study: Model Risk and Model Validation shows your real accuracy, how long you take and where you lose marks.
More Case Study: Model Risk and Model Validation questions
- A bank's validation team is reviewing a newly developed retail credit scorecard. Which activity best represents 'conceptual soundness' asses…
- A validator benchmarks an internal pricing model against a vendor model for 100 exotic trades. The mean absolute price difference is 0.4% of…
- A bank's risk team builds a credit scoring model using customer data from a ten-year period of strong economic growth. After a recession beg…
- In the London Whale case, the modified VaR model computed a hedge-ratio-like volatility measure using a spreadsheet in which a calculation d…
- Long-Term Capital Management (LTCM) collapsed in 1998 despite using sophisticated VaR models. Which model-related weakness best explains why…
- Under SR 11-7, how should a bank treat a model whose validation found significant limitations that cannot be fixed immediately but that the …