CMA Intermediate · Cost Accounting · Employee Costs
A worker at Kaveri Engineering is paid Rs 50 per hour normally and works 52 hours in a week, of which 40 are normal hours. Overtime is paid at double time. The overtime was required by a customer's special rush job. How much of the week's wages is charged directly to that job as overtime premium, under the usual treatment, if the wages for all 52 hours are Rs 3,200 (40 x 50 + 12 x 100)?
The overtime premium is 12 hours times the extra Rs 50 per hour, which is Rs 600. Because the overtime was worked at a customer's request for a specific job, the premium is charged directly to that job instead of being spread over general overheads.
- ARs 600 premium, charged directly to the rush jobCorrect
- BRs 600 premium, charged to factory overheads
- CRs 1,200 premium, charged directly to the rush job
- DRs 1,200 premium, charged to factory overheads
Explanation
Overtime premium is the extra over the normal rate: 12 hours x (Rs 100 - Rs 50) = Rs 600. When overtime is worked at the specific request of a customer, the premium is charged directly to that job. If overtime arises from general pressure of work, the premium goes to overheads. Rs 1,200 wrongly treats the whole overtime pay as premium.
Did you get it right without looking?
One question tells you little. A timed set on Employee Costs shows your real accuracy, how long you take and where you lose marks.
More Employee Costs questions
- Under the Rowan plan, a worker with a time rate of Rs 50 per hour completes a job in 6 hours against an allowed time of 8 hours. What are th…
- A worker's clock card shows 'gate time' of 48 hours in a week, while his job cards show 42 hours spent on jobs. The remaining time is unexpl…
- Which of the following best describes idle time in the context of employee cost?
- From the payroll of Kaveri Textiles, a worker's gross wages are Rs 24,000. Deductions are PF Rs 2,880, ESI Rs 180 and advance recovery Rs 2,…
- Kaveri Textiles has a worker whose basic pay is ₹20,000 per month and DA is ₹5,000. The worker works 200 hours in a month, of which 20 hours…
- Under the Cost Accounting Standard on Employee Cost (CAS 7), which of the following is treated as a component of employee cost?