FRM Part II · FRM Exam Part II · Non-parametric Approaches
An analyst runs a bootstrap on a historical sample of 1,000 daily losses. In each of 200 bootstrap iterations, she draws 1,000 observations with replacement and records the 95% VaR. The average of the 200 VaR estimates is USD 4.10 million, and the standard deviation of those estimates is USD 0.30 million. Using the bootstrap standard error and a normal approximation, what is the approximate 95% confidence interval for VaR (use 1.96)?
The bootstrap standard error equals the standard deviation of the resampled VaR estimates, USD 0.30 million. Multiplying by 1.96 gives about 0.59, so the 95% interval is 4.10 plus or minus 0.59, roughly USD 3.51 million to USD 4.69 million.
- AUSD 3.51 million to USD 4.69 millionCorrect
- BUSD 3.80 million to USD 4.40 million
- CUSD 3.81 million to USD 4.39 million
- DUSD 3.51 million to USD 4.40 million
Explanation
The bootstrap standard error is the standard deviation of the bootstrap VaR estimates, 0.30. The margin is 1.96 x 0.30 = 0.588. The interval is 4.10 +/- 0.588, i.e. 3.512 to 4.688, about 3.51 to 4.69. Using 1 standard error (3.80 to 4.40) understates the interval width.
Did you get it right without looking?
One question tells you little. A timed set on Non-parametric Approaches shows your real accuracy, how long you take and where you lose marks.
More Non-parametric Approaches questions
- A bank uses BRW-weighted historical simulation. Sorted losses (largest first) and their weights are: 12m (weight 0.02), 9m (0.02), 7m (0.03)…
- A risk manager uses basic historical simulation with 500 daily P&L observations to estimate 1-day 99% VaR for a trading portfolio. Which sta…
- A risk manager compares standard historical simulation with bootstrap historical simulation for a 99% VaR on a portfolio with a short 250-da…
- A risk analyst at a trading desk uses historical simulation with a 500-day window to compute 99% one-day VaR. Which of the following is a re…
- A risk manager is considering volatility-weighted historical simulation (Hull-White) instead of BRW age-weighting. Today's EWMA volatility f…
- A bank's market risk team has 1,000 daily P&L observations and wants a VaR estimate that reflects recent market conditions more heavily whil…