An asset manager reviews four events: (1) a trader enters an order with the wrong quantity; (2) a bond issuer misses a coupon payment; (3) a fund cannot sell a large position without a steep price concession; (4) equity prices fall market-wide. Which option correctly classifies the events in order as operational, credit, liquidity and market risk?
The correct mapping is event 1 operational, event 2 credit, event 3 liquidity and event 4 market risk. Order-entry error is human failure, a missed coupon is counterparty default, a costly forced sale is illiquidity, and a market-wide price fall is market risk.
- A(1), (2), (3), (4)Correct
- B(2), (1), (4), (3)
- C(1), (3), (2), (4)
- D(4), (2), (3), (1)
Explanation
A wrong order entry is a human error, hence operational risk. A missed coupon is issuer default, hence credit risk. Inability to sell without price concession is market liquidity risk. A market-wide equity decline is market risk. The other mappings swap categories.
Did you get it right without looking?
One question tells you little. A timed set on The Building Blocks of Risk Management shows your real accuracy, how long you take and where you lose marks.
More The Building Blocks of Risk Management questions
- Which of the following best explains why financial institutions are subject to prudential capital requirements, rather than relying only on …
- A US exporter will receive EUR 5,000,000 in three months and wants to remove exchange rate risk using a forward contract. Which outcome best…
- Two loans each have expected loss of $50,000 and unexpected loss (standard deviation of loss) of $300,000. Their losses have a correlation o…
- Two assets each have a standard deviation of 20%. A portfolio holds them 50/50. Which pair correlation gives a portfolio standard deviation …
- A firm follows a structured risk management process. After identifying its risks, it measures a currency exposure and decides to hedge half …
- A bank estimates that the 99.9% worst-case annual credit loss on a portfolio is USD 95 million, while the expected loss is USD 30 million. U…