CMA Final · Strategic Financial Management · Securitization
An SPV buys a Rs 100 crore receivables pool and issues Senior tranche of Rs 70 crore, Mezzanine of Rs 20 crore and an unrated Equity (first loss) piece of Rs 10 crore. Pool losses over the life are Rs 14 crore, allocated by strict seniority of subordination. What is the loss borne by the Mezzanine tranche, and what is the credit enhancement (as % of pool) available to the Senior tranche before any loss?
Mezzanine bears Rs 4 crore and the Senior tranche has 30% credit enhancement. The equity piece absorbs the first Rs 10 crore of the Rs 14 crore loss, leaving Rs 4 crore for mezzanine, while Rs 30 crore of subordinated tranches sits below Senior in a Rs 100 crore pool.
- ARs 4 crore; 30%Correct
- BRs 4 crore; 10%
- CRs 14 crore; 30%
- DRs 10 crore; 20%
Explanation
Equity absorbs the first Rs 10 crore, leaving Rs 4 crore for Mezzanine; Senior is untouched. Subordination below Senior is 20 + 10 = Rs 30 crore, i.e. 30% of Rs 100 crore. The 10% option counts only the equity piece and ignores the mezzanine cushion.
Did you get it right without looking?
One question tells you little. A timed set on Securitization shows your real accuracy, how long you take and where you lose marks.
More Securitization questions
- A pool of loans of Rs 100 lakh yields cash flows of Rs 40 lakh at the end of each of the next three years (total Rs 120 lakh). PTC investors…
- A pool of Rs 20 crore of receivables is securitised. Senior PTCs of Rs 16 crore are issued and the remaining Rs 4 crore is a subordinated tr…
- In a securitisation transaction in India, a bank (originator) sells a pool of auto loans to a special purpose vehicle (SPV), which issues pa…
- A pool of Rs 200 crore of loans is securitised and sold to an SPV at Rs 196 crore, and the originator provides a cash collateral of Rs 6 cro…
- A bank pools 1,000 housing loans with a total outstanding principal of Rs 200 crore into a trust that issues pass-through certificates (PTCs…
- A pool of receivables has a face value of Rs 80 crore. The SPV issues a senior tranche of Rs 60 crore, a mezzanine tranche of Rs 12 crore an…