Ananya leads a three-person team at a Chennai general insurer. Her team must finish a claims analysis in 12 working days. Her tasks are: data cleaning (3 days), modelling (5 days, which can begin only after data cleaning), and report drafting (4 days, which can begin only after modelling). Which is the best statement about planning?
The tasks are sequential, so the critical path is 3 + 5 + 4 = 12 days, which equals the deadline. There is no slack, and any delay in any task delays the whole project, so Ananya must monitor each step closely.
- AThe critical path takes 12 days, so there is no slack and any delay to these tasks delays the projectCorrect
- BThe critical path takes 8 days, leaving 4 days of slack
- CReport drafting can run in parallel with modelling, saving 4 days
- DData cleaning has slack because it is the shortest task
- Modelling can be skipped if the report starts early
Explanation
The tasks are sequential: 3 + 5 + 4 = 12 days. This equals the deadline, so there is zero slack. Report drafting depends on modelling, so it cannot run in parallel, and task length does not create slack.
Did you get it right without looking?
One question tells you little. A timed set on Mission, business strategy, teamwork and time management shows your real accuracy, how long you take and where you lose marks.
More Mission, business strategy, teamwork and time management questions
- A project team at a Chennai reinsurer must deliver a reserving analysis in four weeks. The team lead, Anita, lists tasks, estimates duration…
- Rohit, an actuarial analyst in Pune, has a reserving model review due in 10 days. He keeps postponing it to answer every incoming email imme…
- A pension consultancy's vision is to be 'the most trusted adviser to Indian employers'. An actuary employed there is asked to soften an adve…
- Sunita manages a six-person actuarial team at a Delhi insurer. She notices she personally rechecks every routine calculation that capable te…
- A team at a Bengaluru reinsurer has 20 hours of capacity this week. Tasks: A needs 8 hours with high value; B needs 6 hours with medium valu…
- Narmada Re, an Indian reinsurer, has a strategic plan to grow in health reinsurance. Its analysis shows: a strong actuarial team with health…