CA Final · Advanced Auditing, Assurance and Professional Ethics · Overview of Audit of Public Sector Undertakings

Aravali Heavy Industries Ltd, a Government company, has a performance audit under way by the C&AG's office. The audit team finds that a plant was commissioned on time and within the sanctioned budget, but runs at 35% capacity because raw material sourcing was not planned. How should the team classify this in terms of the 3Es, and what is the proper conclusion?

The project showed economy in being completed within budget and on time, but effectiveness is doubtful because the plant runs at only 35% capacity and does not deliver its intended output. Performance audit covers public sector companies, so the 3E assessment applies.

  1. AEconomy and efficiency in project execution were met, but effectiveness is in question because the intended output is not being realisedCorrect
  2. BEconomy is not achieved because the budget was not exceeded
  3. CEfficiency is the only concern since low capacity relates only to the cost of inputs
  4. DNo conclusion on the 3Es can be drawn because performance audit applies only to departments and not to companies

Explanation

Economy relates to acquiring resources at low cost; efficiency to the relation between inputs and outputs; effectiveness to achieving objectives. Timely, within-budget execution suggests economy, but 35% utilisation means the objective of the plant is not achieved, so effectiveness is doubtful. Performance audit is also applicable to public sector companies.