CS Professional · Arbitration, Mediation and Conciliation · Arbitral Proceedings, Pleadings and Evidence
Arbitration between Konark Infra and Deccan Cement is under way. Konark wants to prove delivery delays using a document that was merely shown to the conciliator during an earlier failed conciliation. The document is an ordinary delivery challan created in the course of business, years before conciliation. Deccan objects citing section 81. Which analysis best fits the Act?
Section 81 bars only four listed categories: the other party's settlement views, admissions, conciliator's proposals, and willingness to accept a proposal. An ordinary pre-existing delivery challan falls outside them, so the tribunal decides its admissibility and weight under section 19(4).
- ASection 81 bars every document that was ever mentioned in conciliation
- BSection 81 bars only the listed items such as the other party's views, admissions, conciliator's proposals and willingness to accept; a pre-existing business challan is not among them, and the tribunal decides admissibility and weight under section 19(4)Correct
- CSection 81 bars the challan because the tribunal is not bound by the Evidence Act
- DThe challan is admissible only after the Court orders it under section 27
Explanation
Section 81 lists specific categories: views or suggestions, admissions, conciliator's proposals, and willingness to accept a proposal. An independent pre-existing challan is none of these. Its admissibility, relevance, materiality and weight are for the tribunal under section 19(4). Section 27 concerns court assistance in taking evidence and is not a precondition.
Did you get it right without looking?
One question tells you little. A timed set on Arbitral Proceedings, Pleadings and Evidence shows your real accuracy, how long you take and where you lose marks.
More Arbitral Proceedings, Pleadings and Evidence questions
- The agreement between Banyan Infra Ltd and Setu Constructions LLP says nothing about the place of arbitration. Banyan is in Pune, Setu in Na…
- A contract between Sundaram Motors Ltd and Kobe Parts Co. fixes English as the language of arbitral proceedings. Kobe Parts files a written …
- Meridian Infra Ltd applies, with its tribunal's approval, for Court assistance to take evidence from a site engineer. Which item must the ap…
- Before a three-member tribunal, Ashoka Pharma Ltd needs a former employee of Deccan Labs, who refuses to appear voluntarily, to testify. Ash…
- In an arbitration between Veda Textiles Pvt Ltd and Orion Dyes Ltd, the tribunal wants a third-party supplier in Surat, who refuses to atten…
- Meera Exports Pvt Ltd and Tapti Foods Ltd first attempted conciliation, during which Tapti said it might accept a lower settlement figure. C…