Arvind Ltd has a budget of Rs 100 lakh for one year and the following indivisible projects (outlay / NPV, Rs lakh): P 40/12, Q 30/10, R 50/14, S 20/5. Which combination maximises total NPV?

The best combination is Q, R and S, which uses exactly Rs 100 lakh and gives a total NPV of Rs 29 lakh. P, Q and S gives only 27 lakh, and P, Q and R costs 120 lakh, breaching the budget.

  1. AP, Q and S with NPV 27 lakh
  2. BP and R with NPV 26 lakh
  3. CQ, R and S with NPV 29 lakhCorrect
  4. DP, Q and R with NPV 36 lakh

Explanation

Feasible sets within 100: Q+R+S = 100 outlay, NPV 10+14+5 = 29; P+Q+S = 90, NPV 27; P+R = 90, NPV 26; P+Q+R = 120 exceeds budget. Q, R and S gives the highest feasible NPV of 29.