Asha Textiles has a risk register entry with probability of occurrence 0.20 and estimated impact of ₹50 lakh. Management buys a control costing ₹4 lakh that cuts the probability to 0.05 with the impact unchanged. The net benefit of the control (reduction in expected loss less cost) is:
The net benefit is ₹3.5 lakh. Expected loss falls from ₹10 lakh (0.20 × ₹50 lakh) to ₹2.5 lakh (0.05 × ₹50 lakh), a saving of ₹7.5 lakh, from which the ₹4 lakh control cost must be deducted.
- A₹7.5 lakh
- B₹3.5 lakhCorrect
- C₹6 lakh
- D₹10 lakh
Explanation
Expected loss before = 0.20 × 50 = ₹10 lakh; after = 0.05 × 50 = ₹2.5 lakh; reduction = ₹7.5 lakh. Less cost ₹4 lakh gives ₹3.5 lakh. The ₹7.5 lakh option forgets to deduct the control cost.
Did you get it right without looking?
One question tells you little. A timed set on Corporate Risk Management Performance shows your real accuracy, how long you take and where you lose marks.
More Corporate Risk Management Performance questions
- In corporate risk management, which term describes the level of risk an organisation is prepared to accept in pursuit of its strategic objec…
- A firm's portfolio has a one-day 99% Value at Risk of ₹4 crore. Assuming returns are independent and identically distributed and the square-…
- Sundaram Textiles Ltd estimates that a currency movement could cause a loss of Rs 60 lakh with a probability of 0.25 in the coming year. It …
- A firm expects free cash flow of Rs 60 lakh next year growing at 5% perpetually. Its cost of capital is 15%. Using the constant growth model…
- In enterprise risk management, a firm's 'risk appetite' is best described as:
- Vikram Auto has equity beta 1.2 and debt-equity ratio 0.5 (market values). The tax rate is 30% and debt beta is zero. Using the Hamada relat…