CMA Final · Strategic Cost Management · Asset Life Cycle Costing
At Sabarmati Engineering, 70% of an asset's total life cycle cost is typically determined (committed) at the design stage, while only a small portion has actually been spent by then. If total life cycle cost is estimated at Rs 50,00,000, the cost committed at design stage is:
The committed cost at design stage is Rs 35,00,000, being 70 percent of the Rs 50,00,000 total life cycle cost. Design decisions lock in most future costs, so the early stage offers the greatest scope for cost reduction.
- ARs 15,00,000
- BRs 35,00,000Correct
- CRs 20,00,000
- DRs 70,00,000
Explanation
Committed cost = 70% x 50,00,000 = Rs 35,00,000. Rs 15,00,000 is the remaining 30%, a wrong base use.
Did you get it right without looking?
One question tells you little. A timed set on Asset Life Cycle Costing shows your real accuracy, how long you take and where you lose marks.
More Asset Life Cycle Costing questions
- A firm applies life cycle costing to an asset. Which statement about its use in decision making is correct?
- Gupta Engineering estimates that, for an asset with a 6-year life, 70% of total life cycle cost is committed at the design stage although on…
- Narmada Logistics Ltd is considering a truck costing Rs 20,00,000. Annual running cost is Rs 4,00,000 in year 1, rising by Rs 1,00,000 each …
- A firm uses asset life cycle costing for a printing press. Which statement is correct about the treatment of the disposal phase?
- Which of the following is treated as an acquisition-phase cost, rather than an operating-phase cost, when an asset's life cycle cost is buil…
- Which one of the following is treated as a part of the acquisition (pre-ownership) phase in asset life cycle costing, as opposed to the oper…