Auditor Malone & Co is planning the audit of Tessel Co. The audit committee chair asks to see the detailed audit programme, including the exact sample sizes and test timing, so the committee can approve it. What is the most appropriate response under ISA 260?

The auditor should communicate the planned scope and timing of the audit, including significant risks, but avoid detailed discussion of the procedures that could make the audit predictable and reduce its effectiveness. TCWG do not approve the audit programme, and communication should not be delayed until completion.

  1. AProvide the full programme, because TCWG must approve all audit procedures
  2. BRefuse any discussion of planning, as this would breach independence
  3. CCommunicate the planned scope and timing of the audit, including significant risks, while taking care not to compromise the audit's effectiveness by revealing too much detailCorrect
  4. DDelay all communication until the audit is complete

Explanation

ISA 260 requires communication of the planned scope and timing, including significant risks identified. It cautions that detailed discussion could compromise effectiveness, because procedures become predictable. Approval of the programme by TCWG is not required, and delaying communication until the end is inappropriate.