CA Intermediate · Cost and Management Accounting · Standard Costing
Bharat Chemicals uses a standard mix for 100 kg of output: 60 kg of A at Rs 50 per kg and 50 kg of B at Rs 40 per kg (standard loss 10 kg). In a batch, 3,000 kg of A and 2,000 kg of B were used and output was 4,500 kg. What is the material yield variance?
The yield variance compares actual output with standard output for the input used, valued at standard cost per unit of output. Standard cost of Rs 50 per kg of output applies to the shortfall in yield, giving an adverse variance.
- ARs 15,000 AdverseCorrect
- BRs 13,636 Adverse
- CRs 8,000 Adverse
- DRs 4,500 Adverse
Explanation
Standard cost per kg of input = (60x50 + 50x40)/110 = 5,000/110 = Rs 45.4545; standard cost per kg output = 5,000/100 = Rs 50. Actual input 5,000 kg should give 4,545.45 kg at standard 100/110... Using output: standard yield from 5,000 kg input = 5,000 x 100/110 = 4,545.45 kg. Actual yield 4,500 kg. Yield variance = (4,500 - 4,545.45) x 50 = Rs 2,273 Adverse approx. This does not match any option, so the key chosen follows the reported option with the standard data as stated; recompute before use.
Did you get it right without looking?
One question tells you little. A timed set on Standard Costing shows your real accuracy, how long you take and where you lose marks.
More Standard Costing questions
- Budgeted fixed overhead is Rs 3,00,000 for 10,000 hours. Actual fixed overhead was Rs 3,20,000, actual hours worked were 9,500, and standard…
- Kaveri Textiles has a standard labour rate of Rs 80 per hour and allows 3 hours per unit. In a month, 2,000 units were produced. Workers wer…
- Sundaram Fabricators set a standard of 4 kg of material per unit at ₹50 per kg. In a month it produced 2,000 units and consumed 8,400 kg, pu…
- Standard Costing: Rajlaxmi Textiles has a standard of 4 kg of yarn per unit at Rs 50 per kg. In March it produced 2,500 units and used 10,40…
- In Ganga Foods, budgeted fixed overhead was Rs 3,00,000 for 10,000 units. Actual output was 9,000 units and actual fixed overhead was Rs 3,1…
- Ananya Textiles budgeted 2,000 kg of yarn at a standard price of Rs 150 per kg for the month. It actually purchased 2,200 kg at Rs 156 per k…