ACCA Applied Skills · Performance Management · Limiting factors
Brenner Co needs 1,000 units each of components P and Q. Machine hours available are 3,000 and the machine time needed is 2 hours per unit of P and 3 hours per unit of Q. Variable make cost: P $20, Q $30. Buy price: P $26, Q $36. Which component should be bought externally first, and what is the extra cost per machine hour saved?
Component Q should be bought first, at an extra cost of $2 per machine hour saved. P costs $6 extra over 2 hours, which is $3 per hour, while Q costs $6 extra over 3 hours, which is $2 per hour. The lower figure is outsourced first.
- AP, at $3.00 per hour
- BQ, at $2.00 per hourCorrect
- CP, at $2.00 per hour
- DQ, at $3.00 per hour
Explanation
Extra cost of buying P is $6 for 2 hours saved, which is $3 per hour. For Q it is $6 for 3 hours saved, which is $2 per hour. Q is cheapest to outsource per hour saved, so buy Q first. Option A misidentifies the ranking.
Did you get it right without looking?
One question tells you little. A timed set on Limiting factors shows your real accuracy, how long you take and where you lose marks.
More Limiting factors questions
- A company has a single limiting factor of skilled labour. Product M has contribution of $40 per unit and uses 5 hours. Product N has a selli…
- A company uses linear programming to plan production of two products. Which statement about the feasible region and the optimal solution is …
- In a linear programme, the shadow price of machine hours is $5 per hour and the constraint currently limits output to 100 hours. Which state…
- A company makes products X and Y. Machine hours are the only scarce resource. X has a contribution of $24 per unit and uses 3 machine hours;…