The practitioner must be satisfied the criteria are suitable and available to the intended users. ISAE 3000 (Revised) requires criteria that are relevant, complete, reliable, neutral and understandable. They need not be regulator-issued, identical to competitors' criteria, or merely approved by the audit committee.
- AThat the criteria are suitable and will be available to the intended usersCorrect
- BThat the criteria are issued by a statutory regulator
- CThat the criteria are identical to those used by the entity's competitors
- DThat the criteria have been approved by the audit committee only
Explanation
ISAE 3000 (Revised) requires the underlying subject matter to be appropriate and the criteria to be suitable, meaning relevant, complete, reliable, neutral and understandable, and available to intended users. Criteria need not come from a regulator or match competitors. Audit committee approval alone does not make criteria suitable.
Did you get it right without looking?
One question tells you little. A timed set on Audit-related and assurance services shows your real accuracy, how long you take and where you lose marks.
More Audit-related and assurance services questions
- Orlin & Co is performing agreed-upon procedures for Pell Ltd on its export sales. The procedure is to agree the invoice value of 25 selected…
- Which element must be included in a practitioner's report on prospective financial information under ISAE 3400?
- Fenwick & Co is the independent auditor of Daleview plc and has completed its ISRE 2410 review of the interim financial information. It foun…
- Kestrel Ltd asks its audit firm to report on a cash flow forecast for the next two years, to be given to a bank considering a loan. Which st…
- Orchid Ltd's financial statements are being reviewed under ISRE 2400 (Revised) by Marlow LLP. During the review, the practitioner notices th…
- Zenith Retail plc has asked its audit firm to provide a report on its sustainability report. The engagement is not an audit or review of his…