ACCA Strategic Professional · Strategic Business Leader · Identification, assessment and measurement of risk
Brightwell Telecom uses a 5x5 risk matrix. The board notes that managers scoring risks often disagree widely, and that a risk scored 3 for likelihood and 3 for impact is treated identically to one scored 1 for likelihood and 9 for impact on a different scale. Which is the main limitation of the matrix that this illustrates?
The limitation is that matrix scores are subjective and ordinal, so combining them can produce a misleading ranking in which risks with very different profiles look equal, potentially hiding extreme-impact events. Matrices do not need precise historical probabilities and can be applied to strategic risks.
- AMatrices cannot show risks that have occurred in the past
- BScores are subjective and ordinal, so multiplying them may give a misleading ranking that hides extreme-impact risksCorrect
- CMatrices require precise quantified probabilities from historical data
- DMatrices cannot be used for strategic risks
Explanation
Qualitative matrix scores are subjective ordinal ratings, and combining them mathematically can equate very different risk profiles, masking catastrophic low-probability events. Matrices do not need precise historical probabilities, which is why they are used.
Did you get it right without looking?
One question tells you little. A timed set on Identification, assessment and measurement of risk shows your real accuracy, how long you take and where you lose marks.
More Identification, assessment and measurement of risk questions
- Harbour Freight plc, a logistics group, has plotted its risks on a likelihood-impact matrix. A cyber-attack that would shut down its booking…
- Orlan Mining plc faces a political risk in a country where it operates: nationalisation of its mine. Likelihood is judged low, but impact wo…
- Karel Mining's board is described as risk seeking. It has just approved entry into an unstable region with high expected returns, though its…
- Orlo Pharma's board is risk neutral at corporate level and evaluates projects by expected value. Project A yields 10m with certainty. Projec…
- Kallis Energy's board wants to estimate the maximum loss on its commodity portfolio that would not be exceeded on 99% of days over a one-day…
- Davenport Retail's finance team recalculates a new store project's NPV by changing the sales volume assumption by 10% while holding all othe…