Skip to content

ACCA Applied Skills · Performance Management · Budgetary systems and types of budget

Brindle Ltd budgeted sales of 5,000 units with variable cost of $6 per unit and fixed cost of $20,000. Actual sales were 4,500 units, and actual total cost was $46,500. What is the cost variance when measured against the flexed budget?

The cost variance is $500 favourable. Flexing the budget to 4,500 units gives $20,000 fixed plus $27,000 variable, which is $47,000. Actual cost of $46,500 is $500 below that figure, so the variance is favourable.

  1. A$500 adverseCorrect
  2. B$500 favourable
  3. C$3,000 adverse
  4. D$3,000 favourable

Explanation

Flexed budget cost = 20,000 + 4,500 x 6 = $47,000. Actual cost is $46,500, which is $500 lower, so the variance is favourable. Hence the correct answer is $500 favourable in direction; option B is correct. Comparing with the original budget of $50,000 gives $3,500 favourable, which ignores flexing.

Did you get it right without looking?

One question tells you little. A timed set on Budgetary systems and types of budget shows your real accuracy, how long you take and where you lose marks.

More Budgetary systems and types of budget questions