Skip to content

CA Intermediate · Auditing and Ethics · Audit Documentation

CA Rohini is auditing a company and finds that the file for the previous year, signed 30 June, was assembled and closed on 15 July. The firm's quality policy has no longer period. In India, what is the position under SA 230 and SQC 1 on completing the final audit file?

The assembly was in time. The final audit file should be assembled on a timely basis, ordinarily within 60 days of the auditor's report date. Closing the file 15 days after the report date satisfies that, and the one-year figure applies to retention, not assembly.

  1. AAssembly should be completed on a timely basis, ordinarily not later than 60 days after the date of the auditor's report, so the file was in timeCorrect
  2. BAssembly may be done any time within one year after the report date
  3. CAssembly must be done before the report is signed
  4. DAssembly is not required once the audit report has been signed

Explanation

SA 230 requires timely assembly of the final file, and the ICAI standard on quality control sets a period of not more than 60 days from the report date. Closing on 15 July is 15 days after 30 June, which is within this limit. The one-year period is wrong because it is the retention period.

Did you get it right without looking?

One question tells you little. A timed set on Audit Documentation shows your real accuracy, how long you take and where you lose marks.